Sobre nosotros
Servicios prestados:
Bath Installation, Bath Repair, Bathroom Installation, Bathroom Plumbing, Boiler Installation, Boiler Repair, Boiler Servicing, Central Heating Installation, Central Heating Repairs, Complete Bathroom Renovation, Dishwasher Installation, Emergency Plumbing, Kitchen Plumbing, Plumbing Inspection, Plumbing Repairs, Radiator Bleeding, Radiator Installation, Radiator Repair, Roof Heating, Shower Installation, Tap Installation, Tap Repair, Toilet Installation, Toilet Repair, Underfloor Heating, Water Heater Installation, Water Heater Repair, Water Softener Installation, Water Softener Repair, Water Testing, Air Source Heat Pumps, Gas Safety Certificates - Fixed Price
Zonas de trabajo
Beaconsfield, Buckinghamshire, Berkshire, London, Gerrards Cross, The Chalfonts, Great Missenden, Burnham/Maidenhead/Henley/Marl, Prestwood, Stoke Poges, Amersham, M40 corridor, Marylebone, Maidenhead, Henley-on-Thames, Marlow
Premios:
Gas Safe Registered
Categoría
Detalles de la empresa
Nombre de la empresa
CJD Plumbing and Heating LTD
Número de teléfono
+44 7796 328782
Página web
Dirección
109 Station Road
Beaconsfield HP9 1UT
Reino Unido
Coste medio de proyectos
0 GBP - 50.000 GBP
Seguidores
Credenciales
1 álbum de ideas
CJD Plumbing and Heating LTD |
Your review is inappropriate.
We have the engineers report, the commissioning checklist and warranty validation record which is filled out on completion of every boiler installation. There is a section within this report that covers a tightness test on the gas pipework; our engineer has filled this out accordingly and passed off the installation. I do not believe that our engineer left the test nipple open. Furthermore the boiler would not operate if there was a gas leak within the boiler casing and we left the boiler running.
The installation was completed on 13/01/2023 which is OVER 1 YEAR AGO and we have no idea who has worked on the boiler since. We suspect someone has been called into work on it after us as we were not party to the property handover and still have all the original paperwork.
The Worcester’s engineer report dated 17/10/2023 states;
•The gas valve as letting by – this is a manufacturer default on a factory fitted part.
•Flue not sealed – Builder insisted he would carry this out as he had some externals works to finish.
•Gas nipple left open – Worcester’s report was 9 months after CJD signed off the install. I don’t believe we left it open and gas was leaking for 9 months without anyone mentioning a smell of gas.
We have conversed with you regarding this matter and advised the correct process you should follow.