HELP HELP - contractor added the original and mid work quotes incorrectly. He forgot to carry over the figure onto page 2. So now the work has been completed, he now says I MUST pay him an additional 10,000 (so 50k, not 40k for the refurbishment of a 55 sq mtr open plan apartment (excluding floors and kitchen)
The work is excellent, and the work has been completed, but I had asked for monthly updates to review the budget, and continually he said that the budget was totalled circa 40k)
Do I really have to pay the 10,000? I have since gone through the new invoice with a fine tooth comb, and reduced it somewhat, but it is still 9,000 more to pay. He said he could offer a payment plan over eight months, but I have not agreed or signed confirming this.
Please advise.
This is in SPAIN.
Cruca Interiorismo
livinbarcelonaAutor original
Cruca Interiorismo
livinbarcelonaAutor original
Cruca Interiorismo